Duke can charge ratepayers for time construction delayed on Edwardsport plant
The Indiana Court of Appeals has affirmed grant of Duke Energy Indiana’s request to include the amount spent during an 80-day delay in construction of the coal gasification plant in Edwardsport in a rate adjustment rider. Several parties intervened, claiming construction delays attributable to Duke should not be chargeable to ratepayers.